Ohio
Preliminary Notice-Public Works

Warning: All information contained within this data base is subject to change at any time by the various states and is not guaranteed in any way by FWM Software. Nor does FWM Software assume any liability or responsibility for its content. Please use in conjunction with advice from your attorney.

Note: This information is limited in scope and applies only to this document. Please see the general information, all forms memo, and the general information memo for this type of document, for additional information.

Document Title: Notice of Right to Lien for Furnishing Labor, Materials or Equipment and Request for Copy of Payment Bond.

Scope: State of Ohio, Public Works.

Time Constraints: Subcontractors and Material men: Serve the Notice of Right to Lien upon the general contractor and public entity within 21 days, inclusive, of the first furnishing of labor, materials or services. The notice maybe served after that date, but your claim will cover materials or services provides 21 days prior and subsequently to the date of service. The notice also makes demand for a copy of the jobs surety bond.

Information Requirements: The information required by program and whether you intend to send an owner cover letter.

Form Types: Notice of Right to Lien for Furnishing Labor, Materials or Equipment and Request for Copy of Payment Bond, Exhibits A-D (if needed) and Owner Letter (if used).

Procedures: Enter the program data, including Additional Legal Parties or Releases for Other Companies. Copies of all of the forms must be sent to all public entities involved.

Important: Obtaining the public bond information, and filing against that bond, may represent your only chance of recovery if all public funds have been disbursed. We strongly urge you to obtain this information if at all possible.