New Hampshire
Notice of Intent to Lien-Private

Warning: All information contained within this data base is subject to change at any time by the various states and is not guaranteed in any way by FWM Software. Nor does FWM Software, assume any liability or responsibility for its content. Please use in conjunction with advice from your attorney.

Note: This information is limited in scope and applies only to this document. Please see the general information, all forms memo, and the general information memo for this type of document, for additional information.

Document Title: Notice of Intent to Lien.  Note: This document is printed under the Lien Warning Notice area.  Monthly, follow up deliveries are followed with Statements of Account, also within the Lien Warning Notice area.

Scope: State of New Hampshire, Private Works

Time Constraints: Serve on all parties, owner, general contractor and customer, after every delivery, and 15 days before filing a Lien Attachment.

Information Requirements: The information required by the program.

Form Types: Notice of Intent to Lien, and related documents.

Procedures: Enter the program data, including Additional Legal Parties or Releases for Other Companies. Copies of all of the forms should be send to the owner and general contractor, if any.

Important: This notice is required before filing a mechanic’ lien or bond claim. Subsequent deliveries for the same job require you send a Statement of Account.