Preliminary Notice-Public Work

Warning: All information contained within this data base is subject to change at any time by the various states and is not guaranteed in any way by FWM Software. Nor does FWM Software assume any liability or responsibility for it's content. Please use in conjunction with advice from your attorney.

Note: This information is limited in scope and applies only to this document. Please see the general information, all forms memo, and the general information memo for this type of document, for additional information.

Description: Notice of Right to Lien and Request for Copy Of Public Bond.

Scope: State of Minnesota, Public Work.

Time Constraints: Send anytime after the start of furnishing. While there is no public preliminary notice requirement specifically for this state, you may have right to a Public Improvement lien on unpaid funds or a claim on the project bonds. The public entity is required to send you a copy of the payment and performance bonds upon demand. See the Minnesota Bond or Lien Claim, Public Works, record for more information.

If you do not have a copy of the surety bond already, we strongly urge you to send this form. If you do have the information, you are ready to file your public lien claim.

Information Requirements: The information required by program.

Form Types: Notice of Right to Lien and Request for Copy Of Public Bond, Exhibits A-D (if needed) and Owner Letter (if used).

Procedures: Enter the program data, including Additional Legal Parties or Releases for Other Companies. Copies of all of the forms must be sent to all public entities involved.

Important: Obtaining the public bond information, and filing against that bond, may represent your only chance of recovery if all public funds have been disbursed. We strongly urge you to obtain this information if at all possible.